Progress
Things are changing quickly around here. Nick and his dad have gotten a
lot done. The boiler is hung and now they're completing the plumbing.
The drains for the new half bath are installed on the first floor and
the sub floor repaired. The beadboard is off of the front porch. The
back corner of our house is gone and it's been framed in as part of the
kitchen. The back door is finished and ready to be hung and it's
framed. The sink and dishwasher were taken out this morning, and
hopefully the sink will be temporarily installed soon. The items are
getting crossed off our list quickly. The ones that are left will take
longer to complete. I used the heat gun for the first time yesterday
and it worked pretty well. Right now I'm going to put on the respirator
and go out and see if I can get the paint off of the nook window so it
can be re-installed in its new location. We'll have more detailed posts
and pictures later in the week- there's not a lot of stopping around
here, but the progress is good.